The 120 % Solar Rule Explained: What It Means for Homeowners in 2025

The 120 % Solar Rule Explained

TL;DR – There are actually two “120 % rules” in solar.

  1. A utility sizing cap that limits how much PV you can connect relative to your past or expected electricity use.
  2. The NEC 120 % busbar rule that limits how big the back‑fed solar breaker can be inside your main service panel.
    Understanding both is critical to designing a system that will pass inspection and deliver the financial return you expect.

1. Quick Primer: Two Different 120 % Rules

RuleWhat It GovernsSimple FormulaTypical Outcome
Net‑metering sizing capThe maximum annual energy your PV system may produce relative to 12‑month utility dataAllowed kWh = Last‑year kWh × 1.20Caps array size (e.g., 9 MWh × 1.2 → 7.7 kW‑DC)
NEC 705.12(D)(2) busbar ruleThe combined amperage of the utility main breaker + PV back‑feed breakerMain A + PV A ≤ Busbar A × 1.2Often limits PV breaker to 30–40 A on a 200 A panel

2. Where the 120 % Rule Came From

  • Safety first: Early PV codes worried that a fully producing array plus a fully loaded house could overheat the panel busbar, so the National Electrical Code (NEC) introduced the 120 % factor to add a buffer. (mayfield.energy)
  • Billing fairness: Utilities adopted parallel “offset” caps (usually 100–120 %) so homeowners could not oversize arrays just to be paid retail rates for excess power.
  • Policy evolution: As batteries, EVs and heat pumps push loads higher, many states have relaxed the cap—or scrapped it altogether.

3. State‑by‑State Snapshot (2025)

StateCurrent Sizing CapEffective DateNotes
Colorado200 % of expected average annual consumptionJune 21 2021 (SB 21‑261)Doubled cap to anticipate EV/heat‑pump growth
California150 % under NEM 3.0April 2023Higher cap but lower export credit; batteries strongly advised
Minnesota120 % of production for systems > 40 kW2015 rule; reaffirmed 2024Cap applies mostly to C&I & community solar
Arizona125 % of total connected load (residential); up to 150 % of peak demand (APS C&I)OngoingNet‑billing, no traditional net‑metering
No explicit cap (e.g., TX, FL)Sized only by utility interconnection studiesGood for very large roofs but may face grid‑impact fees

Tip: Caps change fast. Check your utility’s tariff before signing an EPC contract.

4. How to Calculate Your 120 % Limit

  1. Pull the last 12 months of kWh from your utility portal or bills.
  2. Add the kWh (or download the CSV) to find the annual total.
  3. Multiply by 1.2 to get the allowable annual PV production.
  4. Divide by your site’s specific production factor (kWh per kW‑DC) to estimate array size.

Example
• Annual use: 9,000 kWh
• Allowed production: 9,000 × 1.2 = 10,800 kWh
• Southern California production factor: ~1,400 kWh/kW‑DC
• Max array: 10,800 ÷ 1,400 ≈ 7.7 kW‑DC

You can grab your own production factor using the PVWatts tool or by asking our team for a Quick Quote. For more context on household loads, see How many kWh per day is normal?

5. When You’ll Want More Than 120 %

  • Electric vehicles: A single EV can add 3,000–4,500 kWh/yr.
  • Heat‑pump HVAC / water heating: Often doubles electricity use in gas‑to‑electric conversions.
  • Accessory dwelling units (ADUs): California’s Title 24 counts ADU energy under the main meter—plan ahead.
  • Battery‑ready designs: Oversizing the array today improves round‑trip efficiency when you add storage later.

Work‑arounds if your state sticks to 120 %:

  1. Future‑load affidavit: Some utilities allow documented load growth projections (EV purchase agreement, heat‑pump permit).
  2. Community solar or off‑site solar garden: Allowed in CO & MN.
  3. Line‑side tap + main‑panel upgrade: Bypasses the busbar rule altogether (see next section).

6. The NEC 120 % Busbar Rule in Plain English

Think of your service panel busbar like a two‑lane bridge:

  • Lane 1: Utility power flows down through the main breaker (e.g., 200 A).
  • Lane 2: PV power flows up through the solar breaker (often 30–60 A).

The NEC says the sum of those lanes must not exceed 120 % of the bridge’s rating. For a common 200 A busbar:

200 A × 1.2 = 240 A ⇒ Solar breaker ≤ 40 A

Three Ways Around the Busbar Limit

OptionWhat It DoesTypical Cost
Derate the main breaker to 175 ACreates room for a 60 A PV breaker; doesn’t touch busbar$250–$500
Line‑side tapConnects PV on the utility side of the main breaker; NEC 2023 Article 705.11 clarifies methods$600–$1,200
Upgrade to 225 A or 320 A panelFuture‑proofs for EV charging & batteries$2,500–$5,000

7. California Focus—NEM 3.0 After One Year

  • Higher sizing window (150 %) means oversized roofs are finally feasible, but…
  • Export credits average just 4–8 ¢/kWh, so excess generation is worth less than self‑consumption. Batteries shift that excess to evening peaks, dropping payback for PV+storage to 9–11 years on typical homes.
  • Smart‑inverter & rapid‑shutdown rules add minor hardware costs but no size penalty.
  • Proposals to re‑open NEM 3.0 in 2026 could tweak the 150 % figure—design sooner rather than later.

8. Frequently Asked Questions

Q: Does adding a battery raise my 120 % cap?
A: Usually no. The cap is based on array size or expected generation, not storage. But batteries help use excess on‑site, reducing concerns about oversizing.

Q: Does the busbar rule apply off‑grid?
A: No. If you’re disconnected from the utility, Article 705 (interconnection) doesn’t apply. You’ll follow Article 690 instead.

Q: Will the NEC rise 120 %?
A: A proposal to increase it to 125 % failed in the 2023 code cycle. The 2026 cycle may revisit it, but inspectors will enforce today’s 120 % language until your state adopts newer code.

9. Bottom Line & Next Steps

  • The “120 % solar rule” could limit your system for billing or wiring reasons—sometimes both.
  • States like Colorado and California now allow 150–200 % sizing, anticipating electrified homes.
  • Even if your utility still caps at 120 %, smart design (derating, line‑side taps, batteries) can unlock more capacity.
Skip to content